May 2013

The St. Louis County Department of Highways and Traffic, in cooperation with the Missouri Department of Transportation and the Federal Highway Administration, have prepared a Draft Environmental Impact Statement (EIS) for the South County Connector Project.

Draft EIS Review Period
The Draft EIS will be available for review and comment from May 3, 2013 until July 19, 2013. Written comments on the Draft EIS must be postmarked or received by email or mail no later than Friday, July 19, 2013. Written comments should be submitted to:

Mail
St. Louis County Department of Highways and Traffic
Attention: South County Connector
121 S. Meramec Avenue
Clayton, Missouri 63105

Email
JHicks@stlouisco.com

Fax
(314) 615-8532

Draft EIS Public Hearing
Thursday, May 30, 2013
4:00 p.m. - 8:00 p.m.
Shrewsbury City Center
5200 Shrewsbury Avenue
Shrewsbury, Missouri 63119

Project Milestones

Anticipated Milestones Target Dates
Notice of Intent November 2010
Project Open House Public Meeting December 2010
Purpose and Need Statement and Initial Range of Alternatives Early 2011
Public Information Meeting - Purpose and Need/Preliminary Alternatives Spring 2011
Alternatives and Preliminary Draft EIS Summer 2011- Fall 2012
Draft EIS Report April 2013
Public Hearing May 2013
Final EIS Report Fall 2013
Record of Decision Fall 2013